Civil Engineering .. Surveying MCQs with answers - part-1.

 Welcome to edusoars.blogspot.com, we offer a wide range of MCQs on a variety of subjects, including: Computer Science, Engineering, Mathematics, Science, Aptitude, Reasoning, General Knowledge.

 Our MCQs are designed to help you prepare for your competitive exams in the most effective way possible. Each MCQ may comes with a detailed explanation, so you can understand the concept behind the question and learn from your mistakes.

 We also offer a variety of practice quizzes/tests, so you can test your knowledge and see how you stack up against other candidates. Our practice quizzes/tests are designed to be as realistic as possible, so you can be confident that you are prepared for the real exam.

 We are constantly adding new MCQs and practice quizzes/tests to our website, so you can always find new material to study.

 If you are looking for a comprehensive and effective way to prepare for your competitive!!!! exams, then edusoars.blogspot.com is the perfect resource for you. With our wide range of MCQs, practice quizzes/tests, and resources, you can be confident that you will be ready for the real exam.

 Thank you for visiting edusoars.blogspot.com. We wish you the best of luck in your studies!
Civil Engineering

Surveying MCQs with answers - part-1



1. A check line in a chain surveying ?


a] checks the accuracy of the framework 


b] enables the surveyor to locate the interior details which are far away from the main chain lines 


c] fixes up the directions of all other lines 


d] all of the above 


Answer: checks the accuracy of the framework



2. A plain scale is used to read ?


a] one dimension 


b] two dimensions 


c] three dimensions 


d] all of these 


Answer: two dimensions



3. The method of measuring distance by pacing is chiefly used in ?


a] reconnaissance surveys 


b] preliminary surveys 


c] location surveys 


d] all of these 


Answer: reconnaissance surveys



4. Direct ranging is possible only when the end stations are ?


a] close to each other 


b] not more than 100 m apart 


c] mutually intervisible 


d] located at highest points in the sea 


Answer: mutually intervisible



5. When the measured length is less than the actual length, the error is known as ?


a] positive error 


b] negative error 


c] compensating error 


d] instrumental error 


Answer: d] inegative error



6. The tension, at which the effects of pull and sag for a tape are neutralised, is known as ?


a] initial tension 


b] absolute tension 


c] surface tension 


d] normal tension 


Answer: normal tension



7. A plumb bob is required ?


a] when measuring distances along slopes in a hilly country 

b] for accurate centering of a theodolite over a station mark 


c] for testing the verticality of ranging poles 


d] all of the above 


Answer: all of the above


8. When the length of chain used in measuring distance is longer than the standard length, the error in measured distance will be ?


a] positive error 


b] negative error 


c] compensating error 


d] none of these 


Answer: negative error



9. Chain surveying consists of the arrangement of framework of triangles because a triangle is the simple plane figure which can be plotted uniquely if ............... of the triangle are known. ?


a] three sides 


b] three angles 


c] one side and two angles 


d] one angle and two sides 


Answer: three sides



10. The accuracy in laying down the perpendicular offsets and in measuring them depends upon ?


a] scale of plotting 


b] length of offset 


c] importance of the object 


d] all of these 


Answer: all of these